Projects with building permission on or after 01-01-2017 must register (exempt: land up to 500 sq.m or up to 8 units, or pure renovation).
RERA Filings
Quick Reference for Your Business
What Is Filed · Due Dates · Penalties – everything you need to know about RERA Filings.
What Is Filed & Who Must Register
Form 1 (Architect), Form 2 (Engineer), Form 3 (CA Certificate) plus flats sold / booked status.
70% of buyer collections must be kept in a separate project (escrow) account.
Real estate agents must register — valid 5 years.
Information / Documents to Provide
and portal login
and Engineer's certificate (Form 2)
Collection, the 70% separate account, and free account
for the quarter
with amounts received
against the RERA checklist
Due Dates (Quarterly Updates)
| Quarter | Last Date |
|---|---|
| Jan — Mar | 15 April |
| Apr — Jun | 15 July |
| Jul — Sep | 15 October |
| Oct — Dec | 15 January |
File each quarterly update within 15 days of the quarter end. The CA certificate (Form 3) and the 70% escrow are the two points TG-RERA watches most.
Penalties
Penalty up to 10% of the project cost continued violation — imprisonment up to 3 years and / or a further 10%.
₹10,000 per day, up to 5% of the project cost.
Action under the Act — registration can be suspended or revoked.
Why Business Owners Trust Filings Hub
Experienced professionals to handle your tax, GST, accounting and compliance needs with confidence.
Serving businesses, professionals, firms and individuals with practical tax and compliance support.
We track every deadline — no fines, no interest, no surprises.
From registrations and filings to ongoing compliance — we help keep your business on track.
Practical guidance to identify compliance issues, resolve them correctly and keep your business compliant.